MEG Energy
Calgary, AB
Construction Management
Tenant Improvement
Shortly after Govan Brown partnered with MEG Energy, the energy sector took a hit due to oil prices, which stalled construction kickoff of MEG’s new offices. This was an opportunity to truly leverage the design-build/construction management partnership the team had established. Our team was able to capitalize on the stalled start and mitigate future roadblocks by working diligently with the design team and the client during the extended pre-construction period on creative phasing, budgeting, and constructability. Our team was also critical in scheduling the project and working with the client to establish detailed monthly cost reports, which the client used to obtain TI allowances from Oxford and ensure that they were always cash-flow-positive throughout the project.